Americus Garden Inn December-Winter-almost Spring Project

Look what I found in the garden today - the first daffodil of the year. That means that the December/Winter project my become the spring project...Here are the latest photos of the renovation project taken in the last couple of days. Remember to click the photos for a better view. The window trim on the Magnolia Suite is being completed.
The gable on the south side of the house has all of the siding removed. Can you tell how tall our house really is?

Siding on the gable has been replaced and the trim is being installed.

Kitchen window has been removed and this is the view from the inside.

This is the view from the outside.


The kitchen window is being installed.

The two men were trying to synchronize their hammering...

Once the window was set, the work started on the siding.


This is where we are as of this afternoon.

They finished the trim work on the gable, and moved the ladders to the other side of the house.

As I was taking the last two photos, I found more evidence of spring. Can you believe it was 75 degrees today?